How to install HDPE Electrofusion pipe fittings

Views: 0     Author: ERA Technical Team     Publish Time: 2024-11-26      Origin: Site

Inquire

facebook sharing button
twitter sharing button
line sharing button
wechat sharing button
linkedin sharing button
pinterest sharing button
whatsapp sharing button
sharethis sharing button

Introduction:

HDPE electrofusion fittings are widely used in various industries due to their reliability, durability, and ease of installation. Proper installation is crucial to ensure the strength and integrity of the joint, preventing leaks and prolonging the pipeline's service life. This guide provides detailed step-by-step instructions for installing HDPE electrofusion fittings, including preparation, cleaning, welding, and post-installation care. By following these instructions carefully, you can achieve a secure and long-lasting connection.


Preparation:

1. Prepare PE electrofusion fittings and pipes.

Prepare pipe fitting

2. Gather tools Gather necessary tools:

a. AlcoholGather tools

b. Measuring tape

c. Scraper

d. Dust-free paper

e. Gloves

f. Scissors

g. Markers

h. Scanner

i. Electrofusion welder


Before operation:Cleaning and Inspection

1. Clean the pipe surface:

Use dust-free paper and alcohol to wipe the surface of the pipe.

Clean the pipe surface

2. Inspect the electrofusion fittings:

Take out the fittings with packaging and carefully inspect for any defects.

inspect fittings


Step 1:Marking and Preparing the Pipe

Measure and Mark:

a. Measure the socket depth of the electric fusion fitting and mark the corresponding length on the pipe.

The first step-Measure and Mark

b. Draw cross lines on the pipe surface to ensure the oxide layer is evenly removed.

draw cross line-Purpoese of cross lines


Step 2:Remove the oxide layer on the surface of the pipe.

1. Remove Oxide Layer:

The second step

a. Use a scraper to remove the oxide layer from the pipe surface at a constant speed.11.The second step

remove the oxide layer

b. Note:Do not use angle grinders as they will cause rapid heating and secondary oxidation.

Note-Donot use angle grinders

2.   Inspection:

Ensure the entire surface has been properly scraped.

Ensure surface is scraped

3.   Pareparation before installing:

a. Take out the manual and the electrofusion fitting, and check whether each accessory is complete, if good, start installation.

 Take out manual

b. Insert the oxide-layer-removed pipe end into the fitting, marking aligns with the end according to the socket depth, and repeat the same steps for the other end.

 mark ccording to socket

c. Wiping the socket part.

Wiping the socket part.


Step 3:Cleaning and Installing the Fitting

The third step

1. Spray alcohol on dust-free paper and clean the socket area of both the pipe and fittings.

Spray alcohol-clean the socket area

2. Install the fitting:

a. Insert the pipe end (with the oxide layer removed) into the fitting, ensuring the marked line is flush with the pipe end.

Insert the pipe end

b. Repeat this process for the other end of the pipe an fittings.

same the other end

c. Tighten screws and use a feeler gauge to confirm the assembly gap (≤0.3mm).

Tighten screws32.confirm the assembly gap


Step 4:Welding Operation

The fourth step

Check that the welding machine is functioning normally.

Check welding machine


Step 5:Start Welding:

The fifth step

1. Scan the barcode on the fitting using the scanner.

Scan the barcode

2. Connect the welding machine to the fitting and set the welding voltage and time as per the manual and begin welding.

Connect machine to the fitting

3. Observe the middle cap of the fittings rising during welding, which confirms the completion of pipe welding poeration.

Observe the middle cap

4. After cooling, the welding machine will print a receipt.

After cooling


Step 6:Once welding is completed, sign the data

The sixth step

Important Note:During the welding process and the cooling phase, do not move or step on the pipeline to maintain welding strength.

 Note-not move or step on the pipe


Saddle Fittings Installation45.Note46.not move or step on the pipe47.not impact welding strength

1. Marking and Preparation:

a. Mark and draw lines on saddle fittings according to the shape of the saddle surface.

draw cross lines

b. Mark and draw cross-hatch on fittings and valves according to the socket size.

cross-hatch lines

52. cross-hatch linesc. Remove the oxide layer from the pipe surface using a scraper (avoid angle grinders)

remove the oxide layer

2. Clean the prepared surface with alcohol and ensure no debris remains.

Clean the surface

3.Fitting Installation:

a. Clean the inner surface of the pipe with alcohol (avoid touching the inner wall).

Clean the inner surface-Note

b. Insert the fusion sleeve halfway into the fitting according to the scale lines.

Insert the fusion sleeve halfway

c. Mark the joints at both ends of the sleeve.

Mark the joints

4. Welding:

Follow the same welding steps as outlined above.


Tapping Tee Installation

1. Close the valve to ensure in a sealed state.

Close the valve

2. Unscrew the black cap of the tapping tee.

Unscrew the black cap

3. Align the “T” wrench of      the special hole-opening tool with the hexagonal slot of the built-in tool.

Align the “T” wrench

4. Hold the "T" wrench and turn the outer cap of the toolo make the outer cap screwed and connected with the saddle.(Note:Tapping tee can be installied under air-carrying working condition.)

Align the “T” wrench

5. Rotate the wrench clockwise to reach the drilling surface.If resistance increases, adjust and proceed steadily until the drill reaches the highest point inside the saddle body.

Rotate the wrench clockwise-Note

6. Rotate the tool. (Note: The rotation resistance is very small at this time.) When the ratation resistance becomes large again, it needs to be rotated again until it  cannot be rotated.68. note

Rotate the tool-Note

7. Rotate the outer cap of the special tool counterclockwise until it is separated, remove the tool,and the hole-opening operation is completed.

hole-opening operation

8. Install the outer cap of the tapping tee. (Note:When presssing, use our special outer cap tool)

Install the outer cap of the tapping tee

This completes the connection of the electrofusion fittings and the valve.

connection of ittings and the valve


This is the specific installation video of HDPE electrofusion pipe fittings:https://youtu.be/QdSECd5mXR4?si=us0-fOZlXrx957Kx

If you have any inquiries or needs, please contact ERA pipe fittings.

Compiled by: Mercy Ruan

Contact us
"ERA" plastic pipe export volume has ranked first in China's plastic pipe industry for many continuous years, while the production and sales volume ranked second in the industry.

Quick Links

Product Category

Contact Us
 NO.1118, Huangjiao Road, Jiangkou Street, Huangyan District, Taizhou, Zhejiang, P.R. China
 info@era.com.cn
  +86-576-84279933
 +86-13738606600
 
Copyright ©2023 ERA Co., Ltd. All Rights Reserved.  Sitemap | Privacy Policy | Support By Leadong